Online Examination System Savitribai Phule Pune University

Image
Instructions Link to mock exam instructions Link to user manual for online examination Link to online examination demo video Students will be able to login only after receiving SMS/EMAIL from SPPU Requirements for online examination: 1. Android phone, desktop, laptop (Windows/Linux/Mac) with working front camera as webcam. 2. Please use an updated version of  Google Chrome  or  Mozilla Firefox  only. 3. Please ensure a reliable internet connection. 4. Please ensure your mobile or laptop is fully charged. 5. Please keep required stationery handy with you (pencil, pen, rough sheet etc.) DEMO VIDEO OF MOCK TEST

Civil Engineering Tips – Points to Remember for Civil Site Engineer

Civil Engineering Tips – Points to Remember for Civil Site Engineer


Civil engineer does many activities at construction site and there are certain works which are repetitive in nature. So, some points, tips and tricks which a civil engineer should remember for faster calculations as well as quick solutions to construction site problems.
  • Lapping is not allowed for the bars having diameters more than 36 mm.
  • Chair spacing maximum spacing is 1.00 m (or) 1 No per 1m2.
  • For dowels rod minimum of 12 mm diameter should be used.
  • Chairs minimum of 12 mm diameter bars to be used.
  • Longitudinal reinforcement not less than 0.8% and more than 6% of gross C/S.
  • Minimum bars for square column is 4 No’s and 6 No’s for circular column.
  • Main bars in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the distributors not less than 8 mm and not more than 1/8 of slab thickness.
  • Minimum thickness of slab is 125 mm.
  • Dimension tolerance for cubes + 2 mm.
  • Free fall of concrete is allowed maximum to 1.50m.
  • Lap slices not be used for bar larger than 36 mm.
  • Water absorption of bricks should not be more than 15 %.
  • PH value of the water should not be less than 6.
  • Compressive strength of Bricks is 3.5 N / mm2.
  • In steel reinforcement binding wire required is 8 kg per MT.
  • In soil filling as per IS code, 3 samples should be taken for core cutting test for every 100m2.
Density of Materials
MaterialDensity
Bricks1600 – 1920 kg/m3
Concrete block1920 kg/ m3
Reinforced concrete2310 – 2700 kg/ m3
Curing time of RCC Members for different types of cement
Super Sulphate cement: 7 days
Ordinary Portland cement OPC: 10 days
Minerals & Admixture added cement: 14 days
De-Shuttering time of different RCC Members
RCC MemberDe-shuttering time
For columns, walls, vertical form works16-24 hrs.
Soffit formwork to slabs3 days (props to be refixed after removal)
Soffit to beams props7 days (props to refixed after removal)
Beams spanning upto 4.5m7 days
Beams spanning over 4.5m14 days
Arches spanning up to 6m14 days
Arches spanning over 6m21 days
Cube samples required for different quantity of concrete
Quantity of ConcreteNo. of cubes required
1 – 5 m31 No’s
6 0 15 m32 No’s
16 – 30 m33 No’s
31 – 50 m34 No’s
Above 50 m34 + 1 No’s of addition of each 50 m3

100622-A-4015L-019

Comments

Popular posts from this blog

Collect the information of various type of connection used in actual practice

PRINCIPLES APPLIED ON A LARGE SCALE INDUSTRY